Construction images
Control-command room
Situated between OH2 and EH1, the control command room tries to leave some space free. Main limitation comes from the passing throught of two huge lead tubes.
The Control-Command room houses the beamline control computer and has direct access to all important electronic racks.
September 2003
SPEC master in front of the control computer |
October 2002
EH1
General views
Sample holder
Germanium fluorescence detector
OH1
Impact of the full 2mrad white X-ray beam fan on the water-cooled beam shutter of OH1
Slits
Qualification des courses des fentes réglage des limites et des références |
M1
December 2000: Mirror tests
January 2001: M1 installation on OH1
05 February 2002: M1 base splitting
12 February 2002: M1 cooling system mechanical test
January 2003: installation of a more rigid M1 cooling system
OH2
Monochromator
2002: both LN2 cooling system operationnal
For the first cristal, 2 LN2 cooling systems are available: direct (bottom) and through copper wires (top, presently used)
19 February 2002: first beam through monochromator
30 january 2002: 2nd cristal
Vue d'ensemble du montage
En cours de cablage... Tous les cables (moteurs et jauges) sont regroupés sur deux connecteurs DB25.
L'ensemble du courbeur devra pouvoir être déconnecté du monochromateur le plus aisément possible.
Tous les déplacements sont quantifiés par des jauges de contrainte. Celles-ci permettent également la gestion des limites.
Pour éviter que le 2nd cristal ne chauffe, l'évacuation des calories apportées par les moteurs est primordiale.
Les mouvements sont réalisés par un système de points faibles.
15 janvier 2002: 1st cristal
Support 1er cristal |
Echangeur azote |
|
Installation alimentation azote liquide |
29 novembre 2001: tank and bellows installation
Tank outgoing leak test
Not much space left!
Up-and-down motor: left screw for the axis and right screw for the tank
Piquage des arrivées moteurs (courant et limites) et des thermocouples
Bellows installation
altitude 0 |
altitude 25 with M1 at intermediate inclinaison |
altitude 50 with M1 at maximum inclinaison |
20 novembre 2001: support installation
Octobre 2001: axis metrology
Monochromator's axis of rotation and its McLennan encoder
Septembre 2001: first pieces and assembly
Cuve du monochromateur |
Points faibles... (presque) en vrac |
Support 2nd cristal |
Support de l'axe |
Gilles observe ce qui l'attend... |
Pierre aussi... mais depuis l'intérieur |
3D views